Jobs on cottage with target dates. If these target
dates aren't going to be met, I can bring in subs to help.
- 1. tape and float - 5/30/99 - done
- 2. plumbing and kitchen / bath fixtures -12/7/99 75%
complete
- 3. electrical, internet and multimedia wiring - 12/7/99 50%
complete
- 4. trim and paint inside - 7/4/99
- 5. subfloor - complete
- 6. finish floors, tile and carpet - 8/1/99
- 7. septic tank - 12/12/99
- 6. final inspection and move in - 1/2/00
- 7. complete decks and hot tub - 3/31/00
- 8. foundation repair and strengthening - 6/1/00
- 9. landscaping - 11/15/99
- 10. interior design and furnishings - 11/26/99
- 11. solar electric panels and solar water heating systems
with household inverter (to be installed by Bob Nagy).
- 11. Solstice & house warming party 12/21/99
- 12. Les Y2K Farewell Party 12/28/99
Trash - Take rest of drywall
scraps in Ford van to the trash cans at the head of the roads before trash pick up day
next week. Then bring some trash cans back after trash pickup. Clean up underneath
house.
Volleyball Court - Dig hole
for another volleyball net pole so we can stretch out the net and use it. Creating a new
yard and volleyball turf.
Satellite TV - It costs $50
per month for a full subscription. It's $10 per person.
Folks of Cedar Creek -
Comments/ feedback? Email me at:
terry@spring.net
|